Construction is in Full Swing

  • levee degrade along the north and south ends
  • setback levee embankment construction
  • offset area excavation
  • seepage berm installation
  • topsoil stripping
  • clay material blending and placement

Access to the existing levee and South River Road is limited to the two marinas via Village Parkway. All other portions of South River Road between Locks Drive and Gregory Avenue are closed.

image of southport levee improvement project april 2018 progress

southport levee improvement project picture of levee progess

southport levee improvement projec

southport levee improvement project drone shot april 2018

About

The Southport Levee Improvement Project will implement flood risk-reduction measures along one of the most vulnerable levee segments on the river. The Project extends along the west bank of the river, from just south of the Barge Canal, downstream 5.6 miles to the South Cross Levee. It will bring this section of levee up to current standards with Federal and State levee criteria, as well as provide opportunities for ecosystem restoration and public recreation. The City is planning to construct a Class A bike trail on top of the levee and other park lands are being developed nearby.