6th Street & Cummins Way Traffic Safety Project

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

Status: Design

Updates:

July 2026: B&M will start construction for the street improvements on July 27, 2026, and will approximately end on July 31, 2026. The work will include speed bumps, raised median, bollards, speed feedback signs, striping, and new signs. No Parking signs will be posted on street segments 72 hours prior to beginning of work. 

March 2026: City Council has awarded B&M Builders a construction contract at the March 18, 2026 City Council Meeting. Additionally, the City has selected Webster Engineering as the Construction Management consultant to assist with the construction.  

December 2025: The project team is in the process of completing the final plans and specifications. The project is expected to be advertised to bid in January 2025, with construction expected to start in late March/early April 2026. 

February 2025:  The following exhibit shows the traffic calming solutions, which includes speed bumps, bollards, signage, and striping. 

6th St & Cummins Way Traffic Calming Exhibit

January 6, 2025

The Capital Projects Department is hosting a community workshop on Thursday, January 16, 2025 at the Elkhorn Village Elementary School Multipurpose/Cafeteria Room.

6th St & Cummins Way Community Meeting Flyer Updated

Event Flyer Translations

Russian Translation
Spanish Translation

Project Exhibits and Survey

Exhibits of the proposed improvements presented at the community workshop and a project survey is available at the following website below. The survey is open until February 13, 2025.

https://survey.alchemer.com/s3/8125752/6th-Cummins-Safety-Project-Surve

Project Location:

Intersection of 6th Street and Cummins Way 

6th street and Cummins Way

Background:

The City has prioritized this location to be analyzed for traffic calming and mitigation measures due to neighborhood concerns.  The City has engaged with the neighborhood to access and initiate traffic calming measures.  The traffic calming measures installed in 2022 include stop signs, advance warning signs, and striping. The City is in the process performing a feasibility study to further evaluate the intersection and prepare a comprehensive strategy.  

 

Description or Scope: 

The project objective is to improve safety at the intersection. To accomplish this, the City will prepare a comprehensive traffic calming and mitigation strategy including public outreach, technical studies, feasibility studies, and initial design plans.  

 

Project Benefits: 

The project will improve public safety at the intersection of 6th Street and Cummins Way. 

 

Schedule:  

Design: July 2023 – December 2025

Construction: Spring 2026

 

Cost(s): 

Design - $125,000  

 

Funding: 

Design - Measure E  

 

Contact: 

Christian Asuncion 

Associate Civil Engineer 

Capital Projects Department   

christianas@cityofwestsacramento.org 
 

 

Last Edited 

12/30/2025