Status:

The Project is currently at 35% design and is still pending environmental clearance. On January 21, 2026, City Council approved a contract with Bennett Engineering to proceed with 65% design.

Location:

Harbor Blvd from the US 50 On/Off ramp to Industrial Blvd; Industrial Blvd from Harbor Blvd to the Palamidessi Bridge; Lake Washington Blvd from the Palamidessi Bridge to Southport Parkway; Southport Parkway from Lake Washington Blvd to Promenade Street. 

Description or Scope:

The Southport to Harbor Roadway Project will not only include road rehabilitation but will also incorporate complete streets elements, including utility upgrades, filling sidewalk gaps, and adding bike lanes to enhance safety and to meet the needs of pedestrians, bicyclists, motorists, and public transportation uses.

Project Benefits:

Complete streets projects are designed to enable safe use and efficient movement and are designed to meet the needs of pedestrians, bicyclists, motorists, and public transportation users. In addition, improving pavement conditions will enhance the safety of drivers. 

Tentative Schedule:

2026 2027 2028 2029 2030
Winter Spring  Summer  Fall Winter Spring Summer Fall Winter Spring Summer Fall Winter Spring Summer Fall Winter Spring Summer Fall
35 % Design    
65% Design    
Environmental Clearance      
UPRR Coordination    


Community Outreach
   



Final Design    
Bidding    
Construction    

 

Cost(s):

Phase 1 Design - $569,600 

Phase 2 Design (From 35% to 100% design) – $1.6M

Estimated Construction Costs: (Not currently funded)  

  1. Harbor Blvd - $2,059,112 

  2. Industrial Blvd - $6,530,000 

  3. Lake Washington Blvd - $1,980,000 

  4. Southport Parkway - $21,980,000 

 

Funding:

Phase 1 Design 

Measure G - $1,000,000

SB1 - $500,000

Phase 2 Design 

Regional Surface Transportation Grant (RSTP Grant) - $400,000

Enhanced Infrastructure Financing District (EIFD) - $1,200,000

Construction Phase – TBD 

 

Consultant(s):  

Design Phase 1: Bennett Engineering  Services

Design Phase 2: Bennett Engineering Services

Grant Writing: Dewberry 

 

Additional Resources:

Contact: 

Joanna Ortiz  

Assistant Engineer  

Capital Projects Department  

Joannao@cityofwestsacramento.org 
  

 

Project Boundaries: 

 Southport_Harbor Project Data

 

Proposed improvements:  

Exhibit 1 - Promenade Street to Carlin Drive

Promenade st to Carlin Dr

Exhibit 2 - Carlin Drive to 1,300' East of Ramco Street

Carlin Dr to East of Ranco

Exhibit 3 -1,300' East of Ramco Street to Lake Washington Boulevard

Ranco to Lake Washington

Exhibit 4 -Lake Washington Boulevard to Stone Boulevard

Lake Washington to Stone

Exhibit 5 -Stone Boulevard to Terminal Street

Stone to Terminal

Exhibit 6 -Terminal Street to Harbor Boulevard

Terminal to Harbor

Exhibit 7 - Industrial Boulevard to Beacon Boulevard

 Industrial to Beacon

Lasted Edited

8/12/2026