State Streets Pavement Rehabilitation Project

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option

Project Update September 18, 2025: Slurry Seal Surface Treatment

Our street improvement project is moving into its next phase with slurry seal treatment scheduled for Thursday, September 18, Friday, September 19, and Monday, September 22. Please follow all door hanger and no parking signs.

On these dates, no parking will be allowed after 7:00 AM on posted streets. Vehicles left in restricted areas are subject to towing at the owner’s expense, so please make plans to park on nearby streets that are not posted. Streets will be closed during the work, with access limited to emergency vehicles only. In most cases, the surface dries within four to six hours, and roads are expected to reopen by 5:00 PM each day, weather permitting.

To help the process go smoothly, please:

  • Avoid driving, biking, or walking on freshly sealed surfaces until they are reopened to vehicle traffic.

  • Turn off sprinklers and do not allow water to flow into the gutters.

  • Watch for posted signs and follow any directions from traffic control staff.

Driving or walking on the new surface too soon can damage the treatment, stick to shoes or vehicles, and track onto nearby concrete or driveways.

Once the slurry seal is complete, crews will return over the next month for final restoration work. This will include painting roadway striping and stop bars. Crews will also be raising iron, a process that uncovers manholes and utility covers that were temporarily buried during construction. These finishing touches will ensure the roadways are fully restored and safe for everyday use.

We understand that these temporary closures and parking restrictions can be inconvenient, and we thank you for your patience and cooperation as we complete this important work.

Phase 1 - State Streets Pavement Rehabilitation Project

Map of Phase 1:  Winter work curb and gutter (purple), and curb ramps (blue)

State Streets Rehabilitation Map 10.3.23 

  Map of State Streets Infrastructure Projects

Status:

Construction

 

Location:

The bounds of this Project will be within Stone Blvd, Park Blvd, 15th St, and Jefferson Blvd (Project Map)

 

Background: 

The state streets neighborhood underwent sewer rehabilitation in 2020 and a water main improvement in 2021. The pavement condition in this neighborhood is poor.   

The objective of the State Streets Infrastructure Projects is to correct some of the infrastructure deficiencies identified in the City’s Sewer Master Plan (State Streets Sewer Project),  Water Master Plan Water Master Plan (State Streets Water Main Replacement Project), and Pavement Management Plan.

 

Description: 

The State Streets Pavement Rehabilitation Project consists of two construction phases. Phase One will begin in October 2024 and focus on replacing curbs, gutters, valley gutters, and curb ramps. During this work, you can expect partial road closures, driveway closures, and restricted street parking.

Phase Two will involve resurfacing the streets in the project area using slurry seal and a Hot Mix Asphalt (HMA) treatments. This phase requires full road closures and temporary detours. Phase Two is anticipated to conclude by Fall 2025.

 

Schedule: 

Design Early 2024

Constructability Review April 2024

Bid Closed July2024

Construction Contract Awarded to George Reed August 21, 2024

Ceremonial Ground Breaking at Willie DaPrato Park September 12, 2024 

Constriction Notice to Proceed Issued October 21, 2024

- Winter work will include curb, gutter, valley gutters, and curb ramps.

 Utility Lowering May-July 2025 (Active)

Removal of abandoned water lines, live water-line adjustments, and PG&E gas-line

Road Rehabilitation Anticipated July-Fall 2025

    Pending completion of the Utility Lowering

     

    Construction Cost: 

    $6.7 Million  

     

    Funding: 

    SB1: The Road Repair and Accountability Act of 2017  

    Measure E 

     

    Door Hangers distributed February 13-15, 2024:

    Door Hanger February 2024 English

    Door Hanger February 2024 Spanish

    Door Hanger February 2024 Russian

     

    Letter Mailed October 15, 2024:

    Letter Mailed October 2024 English

     

    Consultant(s): 

    Bennett Engineering - Design - Approved July 19, 2023

    George Reed - Construction - Approved August 21, 2024

    FAQs

    Can a pothole be fixed before then?
    When will the street be fixed?
    Can this project fix the sidewalks?
    What is the purpose of the sidewalk surveys happening now?

    Past Project Updates

    October 23, 2024
    November 6, 2024
    November 13, 2024
    November 27, 2024
    December 13, 2024
    December 20, 2024
    January 8, 2025
    June 3, 2025
    August 13, 2025

     

    Contact: 

    Bernard I. Corrales, EIT

    Project Engineer 

    Assistant Engineer, Capital Project

    (916) 617- 4864

    bernardc@cityofwestsacramento.org

     

    Bridget will be out of the office September 26- October 7 and October 16 and 17. Please contact Bernard for assistance during this time.

    Bridget McGinnis 

    Project Engineer 

    Assistant Engineer, Capital Project

    (916) 617-5033 

     

    Last Edited:  

    August 13, 2025