State Streets Pavement Rehabilitation Project

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option

Project Ribbon Cutting January 22, 2026

Please join us in celebrating the completion of the State Streets Road Rehabilitation Project.

This project marks the final phase of three coordinated capital improvement projects completed in the neighborhood. The earlier water and sewer improvements laid the groundwork for this roadway work, and together these efforts represent a significant investment in long-term infrastructure improvements.

We appreciate the community’s support throughout construction and invite you to join us in recognizing the successful completion of this important milestone.

Willie DaPrato Park 1509 Alabama Ave. 

January 22, 2026 at 10 am 

 

State Streets Ribbon Cutting 2026

State Streets Rehabilitation Map 10.3.23 

  Map of State Streets Infrastructure Projects

Status:

Construction

 

Location:

The bounds of this Project will be within Stone Blvd, Park Blvd, 15th St, and Jefferson Blvd (Project Map)

 

Background: 

The state streets neighborhood underwent sewer rehabilitation in 2020 and a water main improvement in 2021. The pavement condition in this neighborhood is poor.   

The objective of the State Streets Infrastructure Projects is to correct some of the infrastructure deficiencies identified in the City’s Sewer Master Plan (State Streets Sewer Project),  Water Master Plan Water Master Plan (State Streets Water Main Replacement Project), and Pavement Management Plan.

 

Description: 

The State Streets Pavement Rehabilitation Project consists of two construction phases. Phase One will begin in October 2024 and focus on replacing curbs, gutters, valley gutters, and curb ramps. During this work, you can expect partial road closures, driveway closures, and restricted street parking.

Phase Two will involve resurfacing the streets in the project area using slurry seal and a Hot Mix Asphalt (HMA) treatments. This phase requires full road closures and temporary detours. Phase Two is anticipated to conclude by Fall 2025.

 

Schedule: 

Design Early 2024

Constructability Review April 2024

Bid Closed July2024

Construction Contract Awarded to George Reed August 21, 2024

Ceremonial Ground Breaking at Willie DaPrato Park September 12, 2024 

Constriction Notice to Proceed Issued October 21, 2024

- Winter work will include curb, gutter, valley gutters, and curb ramps.

 Utility Lowering May-July 2025

Removal of abandoned water lines, live water-line adjustments, and PG&E gas-line

Road Rehabilitation July-Fall 2025

    Ribbon Cutting Ceremony January 22, 2026

     

     

    Construction Cost: 

    $6.7 Million  

     

    Funding: 

    SB1: The Road Repair and Accountability Act of 2017  

    Measure E 

    Measure 0

     

    Door Hangers distributed February 13-15, 2024:

    Door Hanger February 2024 English

    Door Hanger February 2024 Spanish

    Door Hanger February 2024 Russian

     

    Letter Mailed October 15, 2024:

    Letter Mailed October 2024 English

     

    Consultant(s): 

    Bennett Engineering - Design - Approved July 19, 2023

    George Reed - Construction - Approved August 21, 2024

    Past Project Updates

    October 23, 2024
    November 6, 2024
    November 13, 2024
    November 27, 2024
    December 13, 2024
    December 20, 2024
    January 8, 2025
    June 3, 2025
    August 13, 2025
    September 18, 2025

     

    Contact: 

    Bridget McGinnis 

    Project Engineer 

    Assistant Engineer, Capital Project

    (916) 617-5033 

     

    Last Edited:  

    January 20, 2026