Home MenuState Streets Pavement Rehabilitation Project
Project Ribbon Cutting January 22, 2026
Please join us in celebrating the completion of the State Streets Road Rehabilitation Project.
This project marks the final phase of three coordinated capital improvement projects completed in the neighborhood. The earlier water and sewer improvements laid the groundwork for this roadway work, and together these efforts represent a significant investment in long-term infrastructure improvements.
We appreciate the community’s support throughout construction and invite you to join us in recognizing the successful completion of this important milestone.
Willie DaPrato Park 1509 Alabama Ave.
January 22, 2026 at 10 am
Map of State Streets Infrastructure Projects
Status:
Construction
Location:
The bounds of this Project will be within Stone Blvd, Park Blvd, 15th St, and Jefferson Blvd (Project Map).
Background:
The state streets neighborhood underwent sewer rehabilitation in 2020 and a water main improvement in 2021. The pavement condition in this neighborhood is poor.
The objective of the State Streets Infrastructure Projects is to correct some of the infrastructure deficiencies identified in the City’s Sewer Master Plan (State Streets Sewer Project), Water Master Plan Water Master Plan (State Streets Water Main Replacement Project), and Pavement Management Plan.
Description:
The State Streets Pavement Rehabilitation Project consists of two construction phases. Phase One will begin in October 2024 and focus on replacing curbs, gutters, valley gutters, and curb ramps. During this work, you can expect partial road closures, driveway closures, and restricted street parking.
Phase Two will involve resurfacing the streets in the project area using slurry seal and a Hot Mix Asphalt (HMA) treatments. This phase requires full road closures and temporary detours. Phase Two is anticipated to conclude by Fall 2025.
Schedule:
Design Early 2024
Constructability Review April 2024
Bid Closed July2024
Construction Contract Awarded to George Reed August 21, 2024
Ceremonial Ground Breaking at Willie DaPrato Park September 12, 2024
Constriction Notice to Proceed Issued October 21, 2024
- Winter work will include curb, gutter, valley gutters, and curb ramps.
Utility Lowering May-July 2025
- Removal of abandoned water lines, live water-line adjustments, and PG&E gas-line
Road Rehabilitation July-Fall 2025
Ribbon Cutting Ceremony January 22, 2026
Construction Cost:
$6.7 Million
Funding:
SB1: The Road Repair and Accountability Act of 2017
Measure E
Measure 0
Door Hangers distributed February 13-15, 2024:
Door Hanger February 2024 English
Door Hanger February 2024 Spanish
Door Hanger February 2024 Russian
Letter Mailed October 15, 2024:
Letter Mailed October 2024 English
Consultant(s):
Bennett Engineering - Design - Approved July 19, 2023
George Reed - Construction - Approved August 21, 2024
Additional Resources:
Past Project Updates
Contact:
Bridget McGinnis
Project Engineer
Assistant Engineer, Capital Project
(916) 617-5033