Southport Sacramento River Levee Improvement Project

South River Road Closure Announcement

Southport Levee Improvement Project - September 2018 Update 

Construction for the 2018 season continues to advance as we work towards completion of the remaining major elements of the project. Earthwork embankment placement along the south setback levee is substantially complete with slopes being trimmed and finished. The south fix-in-place section and north setback levee areas continue to receive fill material as they approach final elevations. All slurry wall work (conventional and DMM) along the project has been completed and embankment fill for the north fix-in-place section will commence in September. Levee degrade work at the north inlet/outlet continues and we are currently stabilizing the two south inlet/outlet areas with rock, soil, seed and fabric. Rock placement at the erosion repair site along segment C is more than 50% complete and moving along well. Throughout the month of September and into October, the contractor will continue to construct levee embankment, grade/stabilize the offset areas and finished levee slopes, construct the inlet/outlet areas, and continue erosion site repairs throughout the entire project corridor. The 2018 construction season has been a very busy one for the Southport Project and construction is on track to be substantially complete by the end of this year.

Below are some of the major accomplishments from the 2017 construction season: 

  • Hauled over 600,000 cubic yards of embankment material from the Riverpark Borrow sites
  • Hauled over 93,000 cubic yards of embankment material from Borrow One site and completed restoration work
  • Completed over 15,000 feet of Setback Levee Embankment Construction to working platform grade
  • Completed over 14,200 feet of Slurry Wall installation along Segments B2 through F
  • Roadway construction work (South River Road Realignment, Borrow One Ramp, and Access Road 6 Construction)
  • Well/Septic System Abandonments and Structure Demolition
  • Utility Relocation (PG&E and AT&T)
  • Drainage culvert installations

Updated by Jenn Tran 9/19/18

Click the links below for project photos:

Watch the Facebook Live video of the Southport Sacramento River Levee Groundbreaking Event

Click For a Map of the Project:

If you have any questions regarding the project, call the project hotline: (916) 617-5036

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer